Timeline

24th October- Driveway poured/ kitchen splashback
23rd October- Painting Commenced
20th October- Driveway formwork
17th October- Facade fixing
14th October- Pantry/linen & WIR Shelving
10th October- Shower screens/Mirrors
8th October - Main floor tiling completed
2nd October - Main Floor tiling commenced
1st October- Tapware installed
29th September- Toilets installed/ Electrical completed/Rangehood/ facade ballustrading
25th September- First Coat of paint
18th September- Benchtops installed/Waterproofing to Balcony
17th September-Wet areas tiling completed
12th September- Garage door installed,air conditioning vents cut out, staircase gyprocked
9th September- Tiling commenced
5th September- Rain Water Tank installed
4th September- Kitchen, bathroom cabinets fitted
29th August - Waterproofing wet areas
28th August - Lower Level brick clean
27th August-Doors installed/LOCK UP
26th August- Stairs installed
19th August -Gyprock/Cornices
13th August -Insulation installation
5th August- Lower Roof Completed
31st July - Lower Gutters/Eaves/ Render to Facade
17thJuly-Electrical work completed
15th July-Upper eaves Completed
8th July- Roof tiles completed
1st July 2014- Gutter and Fascia installed
27 June 2014-2nd stage bricking completed
17 June 2014- 2nd stage/1st floor bricking commenced
4 June 2014- 1st stage/ground floor bricking completed
30 May 2014- Ground floor brickwork commenced
21 May 2014- Frame completed
19 May 2014- Windows installed
9 May 2014- Ground floor Frame commenced
1 May 2014 - Slab poured
24 April 2014- piering/frame
17 April 2014 - Site cut
10 April 2014- Fence installed/toilet
21 February 2014 - DA Approval
5 December 2013 - Submitted to council
November 2013 - Colour appointments
July 2013 - Tender presentation/signed



My Blog List

  • Majestic 40 at Gardener's Ridge
    One year on
  • Le Voyage du Château de la Milburn
    Milburn Engagement
  • Our House in Voyager Point
    Tiling almost finished...
  • Building a Majestic 45
    Moved in
  • Our Home for Four!
    Almost There
  • Building Our Washington Home With Wisdom
    How We Did Our Landscape Plan….

Views

Search This Blog

Simple theme. Theme images by andynwt. Powered by Blogger.