October 30, 2014

Kitchen Splashback

Glass Splashback has been installed in the kitchen and butlers kitchen. The colour we selected is Gunmetal Glitz.

A few exciting things have happened this week, we received our PCI letter to confirm our PCI for the 12th of November.

Progress this week:
Doors and staircase have been stained
Door furniture installed
Towel rails fitted to bathrooms
Few bad bricks have been replaced around house
Painting completed

To do:
Glass to staircase
Electrical fittings
Ducted vacuum
Carpet
House clean






October 24, 2014

Driveway

Week 27 -Our driveway has been finally poured. Ongoing discussions re the colour of the driveway going back and forth to landscapers we stuck with gunmetal as originally selected. We were up in the air with the colours as the concreters we telling us that bluestone was darker than gunmetal and we wanted a dark driveway. We also nearly changed it to Charcoal, which I think would also look nice. Overall we are happy with the colour of the driveway and unfortunately as DA conditions state the council concrete cannot be coloured. Would have loved for it to be coloured also although we would have major problems obtaining final completion certificate.

We have not heard from our SS and therefore unaware on how long we have left quite frustrating as things are taking forever and they are not communicating any dates.  I had in mind that the house would be completed by 26 weeks?

 Kitchen splashback was installed (I will be back later for a separate post with pics).
Painting commenced on Thursday
Jobs left to do:
Painting inside/outside(downpipes, lower eaves, front door)
Door furniture/ towel rails
Stair rail staining
Carpet
Ducted vacuum installation
House clean




October 16, 2014

Pantry, Storerooms, WIR shelving and more.

-This week we have seen the shelving installed in the Butlers Pantry, storeroom, cloak room and WIR's. We changed the shelving in the butlers pantry and cloak room.
-The kitchen splashback has been half completed as for some odd reason they did not complete the returns on the splashback and also did not install the glass in the butlers. They will be back we hope.
-The lights in the media room have now been changed to the requested blue lights also.
-Driveway was scheduled for today although with the rain we had the other day no doubt they have been back logged.
-Fencing has been removed around the site also and a site clean up( wohoo finally!)
Painters are not due in till next week we have been told.
So looking like we still have at least 3 weeks till PCI. No dates given yet.
Main Bedroom fitout

Linen upstairs

Cloak Room

Butlers Pantry




October 11, 2014

Getting Closer...

We can see the light at the end of the tunnel. (only just) . Things seem to be getting closer to moving into our brand new home. Its taking shape!
This week we have had the main floor tiling completed, shower screens and mirrors installed.
Forecast for next week rain just in time for our scheduled drive way.
My list of things to do is getting slightly downsized.

Things left to be completed:
Splashback in Kitchen/butlers
Door furniture
Shelving
Painting
Staircase- staircase staining and glass installation
Driveway

House needs a clean very messy!
Powder Room

Powder Room Shower

Boys Bathroom



Laundry


Ensuite shower with Kubis

Ensuite Bath

Butlers Pantry


Messy main floor awaiting grouting