August 29, 2014

Locked Out...

Well we have officially been locked out. No more sticky beaking through the house. It happened all too quickly, tradies have been busy this week. Although we can't complain.
Stairs were installed on Tuesday with a few hiccups, we have now agreed to disagree and continue construction, the stairs are slightly different to the display home although a strangers eye would not see any difference.
Doors were installed on Wednesday and by the afternoon the house was at lock up. How exciting!
We also had the lower level brick cleaned in between all these projects. It looks so good.
Waterproofing was done on Friday although I haven't been able to get in the take some pics.

Kitchen is scheduled for Monday, a waterproofing inspection on Tuesday and Tiling is scheduled for Wednesday.

SS is working towards a completion date of October 11. Which is only 6 weeks away.....


Brick Cleaned

Front Door

Front Door with Translucent Glass

Main Bedroom Door

Storeroom Doors

Under Stairs Door

Upper Lounge Room, doors will be stained in Black Walnut

Stairs (Awaiting Glass panels)




August 22, 2014

Gyprock & Cornices



Gyprock installation commenced on Tuesday. The whole house was gyprocked in 1 day surprisingly. They were back the next day for setting of the gyprock and today the cornices were installed upstairs. Square set downstairs. Outside steps were also bricked up.
Walking through the house today feels so much different now, with the walls and roof gyprocked it looks great.


Future schedule
26th Aug- Stairs
27th Aug- Lock up
28th Aug- waterproofing wet areas
1st Sep - Kitchen

Leisure Room


Square Set around Doors and windows


Kitchen

Hallway

Dining room

Media Room with podium

Hallway from Entry
Ensuite bath

Ensuite

Master Bedroom
Powder Room

Bathroom











August 8, 2014

Update


It's moving along nicely this week. The rendering of the facade has been completed, we are extremely happy with the outcome.
Lower roof tiles have been completed and also the ducted vacuum has been installed.
Carpenter was on site today adding cavity doors and last minute touch ups before insulation and gyprock next week.


Rockcoat Acrylic Render- Colours Foxtail/Surfmist

Back lower roof completed




August 1, 2014

Lower Gutters, fascia and Rendering...

Well finally we had some movement after a little holiday for some.
Yesterday we had the lower gutters and fascia installed and also the rendering commenced.
An update by SS advised the following
4/8- rendering will be completed
4/8 -Roof tiles
5/8 -Ducted Vacuum installation
Carpentry and inspection to follow
(Look past the mess at the front, SS is due for a site cleanup.)




Balcony